Found a Form 36 in your contract paperwork? Here’s what it means now that the house is yours.
When the clock starts
The 90-day period begins on the day of settlement, when the property officially becomes yours. It doesn’t start when you signed the contract.
Whose job is it now?
By going ahead on a Form 36, the legal responsibility and cost of bringing the pool barrier up to standard and getting it certified shifts to you as the new owner. For a shared pool, such as in a unit complex, the pool owner (usually the body corporate) has the 90 days.
Your first two weeks
- Book the original QBCC licensed pool safety inspector who listed the non-compliances on the Form 26/36. This is required by law unless the original inspector is no longer available.
- If the previous owner had a failed inspection, ask your conveyancer or agent for the Form 26. It lists what needed fixing.
- Get quotes and book any fencing work early, because tradies can be booked out.
- Look at the easy fixes first: hinge caps, latches, a CPR sign and moving climbable items.
Don’t forget the standard still applies
A Form 36 is not an exemption from the pool safety standard. The barrier has to comply at all times, not just on inspection day.
If you miss the deadline
You’re left owning a pool with no certificate. The council or QBCC can direct you to fix it and fine you, and you can’t lease the property out until the pool is certified.
Before you buy
If you haven’t signed yet, a pool safety inspection beforehand shows what a Form 36 pool might cost to fix. It gives you something to negotiate with.